Solar bracket manufacturer construction and installation process
Sep 14, 2018
According to the construction drawings, combined with the construction site, determine the installation sequence. The Solar bracket modules are valuable items. It is required to be lightly handled during installation and placed in a fixed piece to prevent the components from being damaged. Strictly control the gap between components and components during installation to achieve horizontal and vertical.
1 The components are loosely fixed one by one on the bracket stringer.
2 Refer to the drawing to keep the uniformity of each piece.
3 Fasten all components.
4 Group string connection according to electrical drawings. In order to ensure the reliability of the string connection, it is necessary to carefully follow the operation specifications when carrying out the work.
Grid inverter
3, grid-connected inverter
In the photovoltaic grid-connected system is at a critical position, it can convert the Solar bracket side of the electrical energy into AC power and then connect to the step-up transformer.
Grid inverters are generally heavy, so the installation must be reliable in the installation process.
When wiring, make sure that the switch at the grid point and the DC breaker in the DC side header are disconnected.
Wiring operation must be carried out in strict accordance with the specifications of the model inverter.
Special attention to the inverter output, A, B, C corresponding to the boost input terminal one-to-one correspondence.
RS485 communication line is sent to the upper computer in the substation. The RS485 communication line must use twisted-pair shielded wires and ground the shield reliably to prevent interference.
The roof power station is a home photovoltaic power station, using its own idle roof resources, a set Solar bracket generation equipment not only saves electricity bills from household electricity, but also sells it to the power grid. The most important thing is that every time you send electricity, you can get state subsidies, idle roofs to make money, and contribute to environmental protection. !
1 The components are loosely fixed one by one on the bracket stringer.
2 Refer to the drawing to keep the uniformity of each piece.
3 Fasten all components.
4 Group string connection according to electrical drawings. In order to ensure the reliability of the string connection, it is necessary to carefully follow the operation specifications when carrying out the work.
Wire laying
Grid inverter
3, grid-connected inverter
In the photovoltaic grid-connected system is at a critical position, it can convert the Solar bracket DC side of the electrical energy into AC power and then connect to the step-up transformer.
Grid inverters are generally heavy, so the installation must be reliable in the installation process.
When wiring, make sure that the switch at the grid point and the DC breaker in the DC side header are disconnected.
Wiring operation must be carried out in strict accordance with the specifications of the model inverter.
Special attention to the inverter output, A, B, C corresponding to the boost input terminal one-to-one correspondence.
RS485 communication line is sent to the upper computer in the substation. The RS485 communication line must use twisted-pair shielded wires and ground the shield reliably to prevent interference.